Build Blog - 2 - December 2012
4th December 2012
Today we have had the lorries and the steel at LGF, its great to see the steel going into the ground! Make sure you keep watching the live stream!
7th December 2012
Safety netting in, Scaffold edge protection in, insulated roof panels have arrived.
Will the roof start tomorrow, pray for good weather.
We can't start if there are high winds or if there is a frost which would cause the blokes to slip of the edge.
14th December 2012
We concrete tomorrow!
18th December 2012
Lower concrete floor slab for the bouldering area concreted yesterday, we are now preparing for the main slab pour for Thursday.
Keep your fingers crossed for good weather and we will have all the concrete in before Christmas.
21st December 2012
Today we saw the end to what has been a great few weeks construction onsite for our climbing barn for this year. The initial structure is now completely up with the concrete slab and roof, ready to be fitted out with the climbing wall! Here are some pictures from the final pour.