Build Blog - 13 - February 2014
15th February 2014
We are now into our second year of construction at Lower Grange Farm on our brand new magnificent Climbing Facility. With thanks to the Fundraising Team we have managed to raise the required amount to complete the project!
So, what's been happening?
The contractors have done a great job fitting out the climbing barn inside and out. The outside is now cladded all the way round, with doors hung and cladded too!
The inside has been plaster boarded throughout and with thanks to the Active Support members, this has been filled, sanded and prepared and now has started to be painted. The climbing wall itself is now all primed ready to be decorated in vibrant colours! Up on the Gallery, the floorboards have been fitted and the supports for the glass bannisters have been fitted and measured for the glass.
The project is coming along nicely!
19th February 2014
We are at the stage of designing and painting the rest of the climbing wall but are calling on help from anyone across the county with ideas on how we paint it. You can see below pictures of the areas that require designs as well as an example of the colours we have at our disposal. Feel free to play around with colours and designs, share this amongst anyone you think may be interested.