Build Blog - 1 - November 2012

Build Blog - 1 - November 2012

These entries were written in a blog style as the build developed which has been created here.

1st November 2012

Today we had two young people at Lower Grange Farm(LGF) to set up a camera for our live video stream onto the website. By the end of the today we have the camera set up and running live!

6th November 2012

Maidstone Archaeological team starting today checking the site and surrounding. 

Not only a metal detection but also resistivity testing (looking for under ground, walls, ditches and stuff)

15th November 2012

We can at last add a new chapter to Kent Scouts history at Lower Grange Farm! As of 7:30am on Monday 19th November the contractors arrived on site and started work on our brand new climbing centre!

21st November 2012

Today we cut through the capping layer at each of the base locations, excavate for the column base, set up all the bolts for the steels and concrete them in place.

22nd November 2012

Concrete pad foundations complete.

All 12 bases are now concreted with the holding down bolts for the steel structure positioned.

We now enter a one week curing period where the concrete gains enough strength to take the massive steel structure that goes on it.

24th November 2012

KM Photo shoot celebrating the start of construction. 

30th November 2012

Steel erectors confirm the structural steel arrived on Tuesday and will be going up straight away.

 